February 2015 Special

The Botkins Board of Education met for a Special Board meeting on February 17, 2015. The Board took the following actions:

v Waived the reading of the minutes of the February 11, 2015 regular board meeting.

v Approved the resolution as presented to accept the recommendation of the Authorized Representatives, Construction Manager and Architect to award the base bid and any alternates for said Bid Package to the bidder as provided below as the lowest responsible bidder contingent upon compliance with all conditions precedent to contract execution under paragraph Instructions to Bidders (“IB”) 7.3:

Bid Package Lowest Responsible Bidder Amount

#601 – Demolition and Button-Up Muhlenkamp Building Corp.

Base Bid $1,235,099.00

Alternate – Asphalt $85,230.00

$ 1,320,329.00